Month End Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by daniella

Page: 11 / 127

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2024 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1702 Q&A's Shared By: daniella
Question 44

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two)

Options:

A.

Discuss the issue with the external supplier's authority.

B.

Review the lessons learned from similar past projects.

C.

Gather additional information and estimate the impact.

D.

Update the risk log and bring this up in the meeting with the client.

E.

Wait for the client to raise a concern and collect more information.

Discussion
Question 45

Drag the items on left side to the matching term within the correct project approach on the right side.

Questions 45

Options:

Discussion
Question 46

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Options:

A.

Negotiate a contract change with the subcontractor.

B.

Meet with the client to discuss the issue with the subcontractor.

C.

Inform the subcontractor that they must send the schedule.

D.

Tell the subcontractor to submit a draft schedule.

Discussion
Question 47

A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the

scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.

What should the project manager do in this situation?

Options:

A.

Reject the workload back to the global team.

B.

Assess the team's capacity to absorb the workload.

C.

Evaluate and understand the cause of the conflict.

D.

Escalate the situation to the project sponsor.

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Sep 25, 2024
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 29, 2024
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Sep 13, 2024
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Page: 11 / 127
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599