Big Halloween Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by allegra

Page: 17 / 44

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 594 Q&A's Shared By: allegra
Question 68

A large, multinational organization is reevaluating its policy on project management approaches. Team members are complaining about having different processes for each project they are on. Currently, predictive, agile, and hybrid methodologies are being used. A project manager is now part of a team working on standard criteria for approach selection for new projects.

What should the project manager recommend?

Options:

A.

Identify the most commonly used methodology currently and apply that to all future projects.

B.

Determine the types of projects, constraints, and resources to initiate standard tailoring.

C.

Incorporate both structure and flexibility through custom tailoring for all projects.

D.

Simplify the approaches to use either a single agile or a single predictive methodology.

Discussion
Question 69

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

    Update the issue log and refer to the resource management plan to address the situation.

    Ask the team for extra work to fulfill the project commitment.

    Reduce the scope of the project and inform stakeholders.

Options:

A.

Ask the sponsor for an experienced team member in the company to help the project team.

Discussion
Question 70

A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.

How should the project manager handle the situation?

Options:

A.

Review validation and control procedures.

B.

Discuss reducing interruptions with the sponsor.

C.

Perform stakeholder requirements activities.

D.

Approach the sponsor about using an agile approach.

Discussion
Question 71

A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.

What should the project lead do to obtain the needed resources?

Options:

A.

Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.

B.

Prepare to perform the duties of the cost controller for the duration of the project.

C.

Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.

D.

Inform the project sponsor and initiate a recruitment exercise outside of the PMO.

Discussion
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Sep 15, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Sep 25, 2025
Yeah, definitely. I experienced the same.
Inaaya
Are these Dumps worth buying?
Fraser Sep 2, 2025
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Sep 22, 2025
That's great to know. So, you think new students should buy these dumps?
Page: 17 / 44
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599