Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by bowen

Page: 30 / 159

PMI PMP Exam Overview :

Exam Name: Project Management Professional (PMBOK 7th Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2134 Q&A's Shared By: bowen
Question 120

A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.

What should the project manager do?

Options:

A.

Decline the team member's request as it might jeopardize the schedule.

B.

Approve the team member's request as it will increase motivation.

C.

Decline the team member's request since the goal is not individual team member advancement.

D.

Approve the team member's request on condition they work additional hours when they return from training.

Discussion
Question 121

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

Options:

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Discussion
Question 122

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

Options:

A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

Discussion
Question 123

A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?

Options:

A.

Give some advice to the team member to reduce their stress and anxiety.

B.

Review team participation in the next retrospective meeting with all team members.

C.

Reach out to the team member to discuss and address their concerns as soon as possible.

D.

Evaluate upcoming project deadlines and reorganize team member assignments.

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Feb 23, 2026
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Feb 7, 2026
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Feb 20, 2026
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Feb 24, 2026
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Page: 30 / 159
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599