Black Friday Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by nolan

Page: 13 / 127

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2024 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1702 Q&A's Shared By: nolan
Question 52

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

Options:

A.

Create a risk register to track the risks and request additional budget.

B.

Analyze the impact against the release plan if the blocker is not addressed.

C.

Work with the project owner to prioritize the product backlog.

D.

Escalate the situation to the project sponsor for a possible resolution.

Discussion
Question 53

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?

Options:

A.

Ask the technical team to revise the requirements, even if it requires extra budget.

B.

Arrange a meeting with the client to request additional time to find a new supplier.

C.

Review the existing service contracts to find an option to help procure the vehicles.

D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Sep 14, 2024
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 54

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?

Options:

A.

Support the team in identifying the area of development and address the gap.

B.

Dissolve the team and include the team members in other existing teams.

C.

Identify the struggling team members and move them out of the team.

D.

Set up a clear expectation that the team is to deliver as in their previous projects.

Discussion
Question 55

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?

Options:

A.

Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.

B.

Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.

C.

Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.

D.

Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.

Discussion
Page: 13 / 127
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599