Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by eben

Page: 29 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: eben
Question 116

During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?

Options:

A.

Update the issue log and document the change

B.

Review the product specification requirements.

C.

Perform a root cause analysis

D.

Submit a change request for corrective action.

Discussion
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Jan 8, 2026
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Jan 2, 2026
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jan 23, 2026
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Jan 10, 2026
That's great to know. So, you think new students should buy these dumps?
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Jan 23, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Question 117

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

Options:

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

Discussion
Question 118

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

Discussion
Question 119

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?

Options:

A.

Inform the project steering committee of this constraint.

B.

Inform the project team and create a spike for the next Iteration.

C.

Inform the legal department that the project scope will be updated.

D.

Inform the product owner that the project will continue as planned.

Discussion
Page: 29 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599