New Year Special 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

PMI Updated PMP Exam Questions and Answers by winston

Page: 49 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: winston
Question 196

In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.

Which conflict resolution approach did the project manager use?

Options:

A.

Compromise

B.

Collaborate

C.

Synergy

D.

Force

Discussion
Question 197

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

Options:

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Discussion
Question 198

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

Options:

A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Discussion
Question 199

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?

Options:

A.

Invite the new manager to the next daily scrum.

B.

Invite the new manager to the next sprint review.

C.

Invite the new manager to the next sprint planning.

D.

Invite the new manager to the next sprint retrospective.

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Dec 20, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Dec 21, 2025
That sounds really useful. I'll definitely check it out.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Dec 23, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Dec 16, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Page: 49 / 152
Title
Questions
Posted

PMP
PDF

$99.75  $399

PMP Testing Engine

$112.25  $449

PMP PDF + Testing Engine

$149.75  $599