Special Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by haroon

Page: 23 / 127

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2024 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1702 Q&A's Shared By: haroon
Question 92

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?

Options:

A.

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.

B.

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.

C.

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.

D.

Agree with the project team on a suitable collaboration and make sure information is shared at all times

Discussion
Question 93

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Discussion
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 18, 2024
That sounds really useful. I'll definitely check it out.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 94

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodology

for consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Discussion
Question 95

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

Options:

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

Discussion
Page: 23 / 127
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599