Big 11.11 Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by haroon

Page: 23 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: haroon
Question 92

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

Options:

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Discussion
Question 93

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

Options:

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office's (PMO)assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.

Discussion
Question 94

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

Options:

A.

Discuss the concerns with the project sponsor and modify the project charter to includemore budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Oct 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Oct 14, 2025
YES….. I saw the same questions in the exam.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Oct 26, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 3, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Oct 6, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 95

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Discussion
Page: 23 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599