Question 128

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions whenneeded.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholdersahead of time.

C.

Work with the available stakeholders to make business decisions and keep allunavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders tomake decisions.

Discussion
Question 129

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Discussion
Question 130

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Discussion
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Dec 17, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Nia
Why are these Dumps so important for students these days?
Mary Dec 19, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Dec 15, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Dec 18, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Dec 11, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Question 131

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.