Big Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by renae

Page: 32 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: renae
Question 128

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions whenneeded.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholdersahead of time.

C.

Work with the available stakeholders to make business decisions and keep allunavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders tomake decisions.

Discussion
Question 129

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Discussion
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Oct 10, 2025
That's great to know. So, you think new students should buy these dumps?
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Oct 26, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 1, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 3, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 16, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 130

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Discussion
Question 131

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Discussion
Page: 32 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599