Pre-Winter Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

PMI Updated PMP Exam Questions and Answers by renae

Page: 32 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: renae
Question 128

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions whenneeded.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholdersahead of time.

C.

Work with the available stakeholders to make business decisions and keep allunavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders tomake decisions.

Discussion
Question 129

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Discussion
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Nov 25, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Nov 2, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Nov 8, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Nov 4, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Nov 12, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Question 130

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Discussion
Question 131

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Discussion
Page: 32 / 152
Title
Questions
Posted

PMP
PDF

$159.6  $399

PMP Testing Engine

$179.6  $449

PMP PDF + Testing Engine

$239.6  $599