Exam Name: | Project Management Professional (2024 Version) | ||
Exam Code: | PMP Dumps | ||
Vendor: | PMI | Certification: | Project-Management-Professional |
Questions: | 1702 Q&A's | Shared By: | claire |
An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.
What should the project manager do next?
A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?
A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.
What should the project manager have done to prevent this from happening?
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.
What should the project manager do?