Question 60

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

Options:

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

Discussion
Question 61

A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress

(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.

What should the project manager have done to avoid this situation?

Options:

A.

Stored project documentation in a shared folder.

B.

Organized monthly meetings with the external stakeholders.

C.

Invited all of the stakeholders to daily standup meetings.

D.

Sent weekly status update reports to all of the stakeholders.

Discussion
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 24, 2024
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Question 62

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

Options:

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Discussion
Question 63

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?

Options:

A.

Re-visit the project charter and seek other alternatives.

B.

Proceed and issue the purchase order as this project is important.

C.

Speak with the CEO and ask for their support to approve the offer.

D.

Analyze the bounds of negotiations for project agreements.