A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?
Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project
execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing
emails, which contain useful information but are unmanageable due to the high volume.
What should the project manager do to solve this problem?
Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.
How should the project manager impartially prioritize the requirements to be integrated?
A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.
What should the project manager do?