Big 11.11 Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by safiyyah

Page: 43 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: safiyyah
Question 172

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

Options:

A.

Work on resolving the differences with the key resource and building a good workingrelationship to ensure project success.

B.

Monitor the key resource closely throughout the project, but do not let the projectsponsor know about the conflict.

C.

Request that the key resource's functional manager work directly with the resourceduring the project.

D.

Discuss this with the project sponsor and request that this key resource be replaced onthe project.

Discussion
Question 173

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

Options:

A.

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.

C.

Replace the key team members with new resources who are already aware of the agilemindset.

D.

Provide directions to the team members on how to accelerate the company'stransformation, bringing the project back on track.

Discussion
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Oct 3, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Oct 26, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Oct 17, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Oct 25, 2025
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Question 174

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

Options:

A.

Update the schedule to reflect the holidays and share the workload among offices tomitigate schedule slippage.

B.

Hire additional personnel on a temporary basis to cover the extra workload during theholiday seasons.

C.

Request that the offices in overseas locations work overtime to mitigate scheduleslippages.

D.

Update the schedule to reflect the holidays and notify the project sponsor of thedelayed completion.

Discussion
Question 175

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Discussion
Page: 43 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599