Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMP Exam Questions and Answers by jennifer

Page: 38 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: jennifer
Question 152

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

Options:

A.

Reviewed the risk register to identify a response plan for the audit

B.

Assigned a project team member to ensure all project documentation was updated

C.

Updated the project management plan regularly and had it securely shared with all stakeholders

D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Discussion
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jan 23, 2026
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Jan 13, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Jan 23, 2026
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Jan 19, 2026
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Andrew
Are these dumps helpful?
Jeremiah Jan 19, 2026
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Question 153

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

Options:

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Discussion
Question 154

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

Options:

A.

Increase the overall project duration to account for the inexperienced team memberson the project.

B.

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

Discussion
Question 155

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

Options:

A.

Identify how the proposed changes will benefit the project in relation to the businesscase.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Discussion
Page: 38 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599