Question 80

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

Questions 80

Which of the following calculations accurately shows the critical path?

Options:

A.

20 days

B.

39 days

C.

49 days

D.

52 days

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 81

The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?

Options:

A.

Network diagram

B.

Product backlog

C.

Program

D.

Portfolio

Discussion
Question 82

A developer is experiencing constant project scope changes and reaches out to the project manager to discuss the situation. They agree the customer has requested multiple modifications to the core idea and now extra work may need to be performed. Which of the following approaches would BEST support on-time delivery considering these changes?

Options:

A.

Strict change management controls

B.

Regular Scrum meetings

C.

Continuous requirements gathering

D.

Regular milestone reviews

Discussion
Question 83

Which of the following methods should a project manager use to improve email communication for a time- sensitive, high-visibility global project? (Choose two.)

Options:

A.

Limit email recipients to only required team members.

B.

Increase the number of emails to encourage team interaction.

C.

Set up emails with bold text and all caps in the subject line.

D.

Eliminate acronyms from the email to avoid miscommunication.

E.

Include more information to increase the length of each email message.

F.

Include detailed technical consideration in each email.

Discussion
Page: 20 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99