Question 32

Which of the following will identify the MOST potential project risks?

Options:

A.

Cost-benefit analysis

B.

Past project documentation

C.

Project budget

D.

Benchmarking

Discussion
Question 33

A project manager needs status on the project timeline.

Which of the following team members should provide an update?

Options:

A.

Product owner

B.

Business analyst

C.

Scheduler

D.

Sponsor

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 15, 2025
That's great to hear. I am going to try them soon.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 1, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Nell
Are these dumps reliable?
Ernie Sep 4, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Robin
Cramkey is highly recommended.
Jonah Sep 1, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 34

Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project’s current status.

Which of the following types of reports should the project sponsor use to quickly summarize the status report data?

Options:

A.

Pie chart

B.

Run chart

C.

Project schedule

D.

Dashboard information

Discussion
Question 35

A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?

Options:

A.

Incident response

B.

Quality control

C.

Resource changes

D.

Business continuity response

Discussion