Question 68

The project manager has noticed a vendor is not performing in accordance with the SLA.

Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

Options:

A.

Balanced score card

B.

WBS

C.

Post-project evaluation

D.

PERT

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Question 69

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

  • Coordinate project schedule
  • Manage to the triple constraint
  • Provide performance feedback to team members’ managers

Which of the following types of organizational structures did the new project manager MOST likely join?

Options:

A.

Balanced matrix

B.

Strong matrix

C.

Functional

D.

Projectized

Discussion
Question 70

Which of the following is a key aspect of the Agile project management methodology?

Options:

A.

Test-driven

B.

Daily standup meetings

C.

Short project durations

D.

Defined list of requirements

Discussion
Question 71

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

Options:

A.

Fast-track the tasks.

B.

Utilize positive float.

C.

Crash the schedule.

D.

Remove the critical path

Discussion