Question 64

Which of the following inherently affects quality standards?

Options:

A.

SLA

B.

MOA

C.

MOU

D.

WBS

Discussion
Question 65

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

Options:

A.

Sales clerk

B.

Marketing representative

C.

Team lead

D.

Product item

Discussion
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 66

There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks

A, B, F: 8 weeks

D, E, H: 12 weeks

D, B, F: 7 weeks

Which of the following tasks are on the critical path?

Options:

A.

A, C, G

B.

A, B, F

C.

D, E, H

D.

D, B, F

Discussion
Question 67

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

Options:

A.

SOW

B.

PO

C.

SLA

D.