Question 64

Which of the following inherently affects quality standards?

Options:

A.

SLA

B.

MOA

C.

MOU

D.

WBS

Discussion
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Nov 18, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Nov 25, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Nov 25, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Nov 12, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 65

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

Options:

A.

Sales clerk

B.

Marketing representative

C.

Team lead

D.

Product item

Discussion
Question 66

There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks

A, B, F: 8 weeks

D, E, H: 12 weeks

D, B, F: 7 weeks

Which of the following tasks are on the critical path?

Options:

A.

A, C, G

B.

A, B, F

C.

D, E, H

D.

D, B, F

Discussion
Question 67

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

Options:

A.

SOW

B.

PO

C.

SLA

D.

MOU

Discussion