Question 104

When developing a project schedule, which of the following resources is the BEST to estimate task duration?

Options:

A.

Project manager

B.

Project scheduler

C.

Project team

D.

Project sponsor

Discussion
Question 105

A project manager chose an architect based on the architect’s presentation, but company policy states vendors must be selected based on the lowest bid. Which of the following applies to this situation?

Options:

A.

The PMO did not sign a letter of intent.

B.

The project manager neglected to conduct a communication requirements analysis.

C.

The project sponsor was not consulted in the final decision-making process.

D.

The project manager did not conform to the compliance standard.

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Oct 16, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Oct 7, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 16, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Oct 3, 2025
Me too. They're a lifesaver!
Question 106

Joe, a team member, is dissatisfied with his assigned project tasks, and he communicates this to his manager. His manager arranges a meeting with the project manager. Together, they decide Joe needs additional training to be able to execute the assigned project tasks. Which of the following is the company's organizational structure?

Options:

A.

Projectized

B.

Vertical

C.

Matrix

D.

Functional

Discussion
Question 107

Some resources are waiting to be assigned to a new project. These resources are called:

Options:

A.

underqualified resources.

B.

benched resources.

C.

dedicated resources.

D.

overallocated resources.