Question 104

When developing a project schedule, which of the following resources is the BEST to estimate task duration?

Options:

A.

Project manager

B.

Project scheduler

C.

Project team

D.

Project sponsor

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Oct 18, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Oct 25, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 15, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 1, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Oct 23, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Question 105

A project manager chose an architect based on the architect’s presentation, but company policy states vendors must be selected based on the lowest bid. Which of the following applies to this situation?

Options:

A.

The PMO did not sign a letter of intent.

B.

The project manager neglected to conduct a communication requirements analysis.

C.

The project sponsor was not consulted in the final decision-making process.

D.

The project manager did not conform to the compliance standard.

Discussion
Question 106

Joe, a team member, is dissatisfied with his assigned project tasks, and he communicates this to his manager. His manager arranges a meeting with the project manager. Together, they decide Joe needs additional training to be able to execute the assigned project tasks. Which of the following is the company's organizational structure?

Options:

A.

Projectized

B.

Vertical

C.

Matrix

D.

Functional

Discussion
Question 107

Some resources are waiting to be assigned to a new project. These resources are called:

Options:

A.

underqualified resources.

B.

benched resources.

C.

dedicated resources.

D.

overallocated resources.

Discussion