Question 104

When developing a project schedule, which of the following resources is the BEST to estimate task duration?

Options:

A.

Project manager

B.

Project scheduler

C.

Project team

D.

Project sponsor

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Feb 18, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Feb 8, 2026
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Feb 13, 2026
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Feb 13, 2026
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 105

A project manager chose an architect based on the architect’s presentation, but company policy states vendors must be selected based on the lowest bid. Which of the following applies to this situation?

Options:

A.

The PMO did not sign a letter of intent.

B.

The project manager neglected to conduct a communication requirements analysis.

C.

The project sponsor was not consulted in the final decision-making process.

D.

The project manager did not conform to the compliance standard.

Discussion
Question 106

Joe, a team member, is dissatisfied with his assigned project tasks, and he communicates this to his manager. His manager arranges a meeting with the project manager. Together, they decide Joe needs additional training to be able to execute the assigned project tasks. Which of the following is the company's organizational structure?

Options:

A.

Projectized

B.

Vertical

C.

Matrix

D.

Functional

Discussion
Question 107

Some resources are waiting to be assigned to a new project. These resources are called:

Options:

A.

underqualified resources.

B.

benched resources.

C.

dedicated resources.

D.

overallocated resources.

Discussion