Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

CompTIA Updated PK0-004 Exam Questions and Answers by nala

Page: 9 / 29

CompTIA PK0-004 Exam Overview :

Exam Name: CompTIA Project+ Exam
Exam Code: PK0-004 Dumps
Vendor: CompTIA Certification: Project+
Questions: 796 Q&A's Shared By: nala
Question 36

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.

Which of the following MOST likely explains this issue?

Options:

A.

Risks were not identified.

B.

Risks were not mitigated.

C.

Risks were not exploited.

D.

Risks were not communicated.

Discussion
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Oct 29, 2024
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Question 37

A project manager is required to maintain various documents and procedures.

Which of the following require ongoing attention and periodic updates?

Options:

A.

Project charter

B.

Change requests

C.

Project management plan

D.

Communication plan

E.

Project SOW

Discussion
Question 38

A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and

requested a project manager to work with the firm. The PMO declines to assign a project manager and refers

to another department within the company. Which of the following is MOST likely the reason for this?

Options:

A.

There are not enough project managers available for additional work

B.

The work does not align with the strategic objectives of the organization

C.

This is ongoing work the vendor has been hired to perform

D.

The third party has a reputation for expertise in this area

Discussion
Question 39

A new contractor joining the project team is an example of:

Options:

A.

offshoring

B.

offboarding

C.

rightsizing

D.

outsourcing

Discussion
Page: 9 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99