Question 100

A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?

Options:

A.

Meeting minutes

B.

Issue log

C.

Project schedule

D.

Budget

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Aug 4, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Aug 19, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Aug 21, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Aug 20, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Question 101

A key stakeholder claims to have not received status updates per the agreement. The PM reviews the communications plan and determines the updates were provided as agreed upon. Which of the following should the PM do NEXT to resolve the inconsistency between the communications plan and the stakeholder’s expectations?

Options:

A.

Analyze the RASI chart

B.

Review previous meeting minutes.

C.

Initiate a change control request.

D.

Updates the communications plan.

Discussion
Question 102

A manager is reviewing some projects with two project managers who are working on the financial system.

Which of the following BEST describes this type of review?

Options:

A.

Operations

B.

Project

C.

Portfolio

D.

Program

Discussion
Question 103

A highly skilled, key project team member lacks technical writing skills. Documents are often misunderstood, and the wrong instructions are given.

To retain this key project team member, which of the following steps should the project manager take to BEST resolve the issue?

Options:

A.

Retrain the key project team member.

B.

Replace the key project team member.

C.

Hire a translator to assist the team member.

D.

Accept the key team member's limitations.

Discussion