Question 84

Which of the following is a suitable situation in which to apply the Agile methodology?

Options:

A.

A very well-defined RFP

B.

A fixed price contract

C.

High-level requirements

D.

Clear goals and large teams

Discussion
Question 85

A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources.

Which of the following impacts will MOST likely occur? (Choose two.)

Options:

A.

Cost will increase.

B.

Scope will increase.

C.

Schedule will decrease.

D.

Risk will decrease.

E.

Budget will increase.

F.

Quality will increase.

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Question 86

The project coordinator creates the following list to track the items team members are working on:

Questions 86

Which of the following types of documents is shown in the table above?

Options:

A.

Project schedule

B.

Project charter

C.

Action item log

D.

Work breakdown structure

Discussion
Question 87

During a meeting, the project manager abruptly interrupts the discussion of two team members who have not reached an agreement on a particular requirement and continues with the meeting.

Which of the following conflict resolutions is the project manager performing?

Options:

A.

Smoothing

B.

Forcing

C.

Confronting

D.

Avoiding