Winter Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

CompTIA Updated PK0-004 Exam Questions and Answers by alec

Page: 14 / 29

CompTIA PK0-004 Exam Overview :

Exam Name: CompTIA Project+ Exam
Exam Code: PK0-004 Dumps
Vendor: CompTIA Certification: Project+
Questions: 796 Q&A's Shared By: alec
Question 56

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

Options:

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.

Discussion
Question 57

The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit.

Which of the following actions should the project manager take?

Options:

A.

Initiate change control.

B.

Follow communications plan.

C.

Manage project quality.

D.

Prepare a performance report.

Discussion
Question 58

A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?

Options:

A.

The reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.

B.

The reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.

C.

The reduced timeline will decrease risk, resulting in an increased contingency reserve.

D.

The reduced budget will cause the project manager to reject the change order.

Discussion
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Oct 5, 2024
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 18, 2024
That sounds really useful. I'll definitely check it out.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Aug 8, 2024
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Question 59

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

Options:

A.

SLA

B.

SOW

C.

Change request

D.

RFP

Discussion
Page: 14 / 29
Title
Questions
Posted

PK0-004
PDF

$42  $104.99

PK0-004 Testing Engine

$50  $124.99

PK0-004 PDF + Testing Engine

$66  $164.99