Question 16

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

Options:

A.

Revise the project plan.

B.

Update the issue log.

C.

Request additional funding.

D.

Issue a change request.

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 26, 2024
That's great to know. So, you think new students should buy these dumps?
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Oct 22, 2024
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 24, 2024
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Question 17

Under an Agile methodology, standup meetings occur:

Options:

A.

daily

B.

twice daily

C.

weekly

D.

ad hoc

Discussion
Question 18

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

Options:

A.

Ask the team member to move to a different test environment.

B.

Ask the team member to refrain from testing the scenarios.

C.

Revisit the risk management plan and provide corrective actions.

D.

Revisit the contingency plan and provide corrective actions.

Discussion
Question 19

A resource is assigned to two projects with two scheduled tasks that complete at the same time.

This is known as:

Options:

A.

shared resource contention

B.

intraproject resource contention

C.

interproject resource contention

D.

dedicated resource contention

Discussion