Question 16

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

Options:

A.

Revise the project plan.

B.

Update the issue log.

C.

Request additional funding.

D.

Issue a change request.

Discussion
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Question 17

Under an Agile methodology, standup meetings occur:

Options:

A.

daily

B.

twice daily

C.

weekly

D.

ad hoc

Discussion
Question 18

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

Options:

A.

Ask the team member to move to a different test environment.

B.

Ask the team member to refrain from testing the scenarios.

C.

Revisit the risk management plan and provide corrective actions.

D.

Revisit the contingency plan and provide corrective actions.

Discussion
Question 19

A resource is assigned to two projects with two scheduled tasks that complete at the same time.

This is known as:

Options:

A.

shared resource contention

B.

intraproject resource contention

C.

interproject resource contention

D.

dedicated resource contention

Discussion