Question 92

A project manager holds weekly project status meetings with the project team and an outside contractor. One of the team members is best friends with the contractor, so discussions often go off-track and meetings last longer than planned. Which of the following is the BEST step for the project manager to take to resolve this issue?

Options:

A.

Establish what will be discussed before the meeting and ensure the agenda is followed.

B.

Talk to the team member about keeping personal discussions outside the meeting.

C.

Reinforce the established project communication plan.

D.

Take charge of the meeting by not allowing side-talking.

Discussion
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Nell
Are these dumps reliable?
Ernie Oct 10, 2024
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Question 93

A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial.

This would MOST likely impact the project’s: (Choose two.)

Options:

A.

environment

B.

scheduling

C.

requirements

D.

effectiveness

E.

scope

F.

budget

Discussion
Question 94

A project team decides to obtain a support contact on one of the hardware infrastructures being used on the project. This is to ensure the project is grounded if an issue with the hardware occurs during the course of the project.

This type of risk response is known as:

Options:

A.

mitigation.

B.

avoidance.

C.

transference.

D.

acceptance.

Discussion
Question 95

Collaboration tools are BEST used instead of email when multiple people are:

Options:

A.

scheduling a meeting.

B.

communicating the agenda for a meeting.

C.

conducting research for a meeting.

D.

working on document for a meeting.

Discussion