Question 96

Agate review also is considered:

Options:

A.

a method to make changes to resources.

B.

an update to an incident response plan

C.

a checkpoint to review schedule changes

D.

a type of audit occurring during the project.

Discussion
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 26, 2024
That's great to know. So, you think new students should buy these dumps?
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Aug 12, 2024
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 97

A project manager conducted an audit of project deliverables. During the audit, the project manager identified a deliverable that did not meet quality standards. Which of the following describes who the project manager should notify FIRST?

Options:

A.

Project team

B.

Project sponsor

C.

Stakeholders

D.

Project champion

E.

Project management office

Discussion
Question 98

A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting. The project manager needs to take the following elements into account:

  • Delivery
  • Vacation
  • Cost of overtime
  • Work effort

Which of the following documents should the project manager use to guarantee the project’s success?

Options:

A.

RACI

B.

Schedule

C.

Project charter

D.

SWOT

E.

Burn chart

Discussion
Question 99

Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)

Options:

A.

Qualitative assessments are more difficult.

B.

Qualitative assessments are faster.

C.

Qualitative assessments require fewer resources.

D.

Qualitative assessments provide more accurate results.

E.

Qualitative assessments better identify opportunities.

Discussion