Question 20

Which of the following statements are correct regarding project management? (Select two.)

Options:

A.

A project can be part of an organization’s program management.

B.

An organization’s portfolio will include programs.

C.

A program has a defined start and finish.

D.

An organization’s portfolio is a temporary and unique endeavor.

E.

A project portfolio will be managed under program management.

Discussion
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 21, 2024
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 25, 2024
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 21

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Questions 21

Which of the following represents the cost variance for both project completions?

Options:

A.

-$4.8K and -$7K

B.

-$4.9K and $7K

C.

$4.8K and -$7K

D.

$4.8K and $7K

Discussion
Question 22

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

Options:

A.

Planned value

B.

Schedule variance

C.

Acceptable variance

D.

Cost variance

E.

Earned value

Discussion
Question 23

A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?

Options:

A.

Project communication plan

B.

Project status report

C.

Project management plan

D.

Project backlog

Discussion