Question 20

Which of the following statements are correct regarding project management? (Select two.)

Options:

A.

A project can be part of an organization’s program management.

B.

An organization’s portfolio will include programs.

C.

A program has a defined start and finish.

D.

An organization’s portfolio is a temporary and unique endeavor.

E.

A project portfolio will be managed under program management.

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 13, 2024
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Question 21

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Questions 21

Which of the following represents the cost variance for both project completions?

Options:

A.

-$4.8K and -$7K

B.

-$4.9K and $7K

C.

$4.8K and -$7K

D.

$4.8K and $7K

Discussion
Question 22

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

Options:

A.

Planned value

B.

Schedule variance

C.

Acceptable variance

D.

Cost variance

E.

Earned value

Discussion
Question 23

A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?

Options:

A.

Project communication plan

B.

Project status report

C.

Project management plan

D.

Project backlog

Discussion