Which of the following statements are correct regarding project management? (Select two.)
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.
Which of the following represents the cost variance for both project completions?
Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?