Question 72

After identifying all known tasks, the project manager has started to sequence and set durations.

Which of the following describes how the project manager should BEST determine the initial sequence and durations?

Options:

A.

Use milestones identified in the project charter.

B.

Use data based on past knowledge.

C.

Hold a full team workshop to review the complete WBS.

D.

Collaborate with other project managers.

Discussion
Question 73

A project manager is creating the WBS.

In which of the following phases is the project?

Options:

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Oct 7, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 3, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 2, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Oct 8, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Question 74

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

Options:

A.

Transfer

B.

Share

C.

Mitigate

D.

Avoid

Discussion
Question 75

Team members have reported that meetings are poorly attended and unproductive.

Which of the following steps can the project manager take to make the meetings more productive?

Options:

A.

Discontinue the meetings with the poorest attendance.

B.

Decrease the length of the meetings.

C.

Distribute an agenda before each meeting.

D.

Document team member attendance and report it to management.