A buyer finds an opportunity to reduce costs for a particular service through competitive bidding. The buyer issues a request for quotation (RFQ) to prequalified suppliers. However, the statement of work is incomplete, and not clear enough to get an accurate price for the service. Which of the following is the BEST course of action for the buyer to take in order to get a proper statement of work included in the RFQ?
A supply manager identifies an overseas source for parts used by the organization. The supplier's capacity, performance, reputation and sample quality are all acceptable. During final price negotiations, the supplier requests that the contract be based on its local currency. Which of the following is the FIRST course of action the supply manager should take in order to address the possible impact of this request?
PQR, Inc. is a globally certified manufacturer and repair shop of aircraft parts. PQR's costs to produce these parts are as follows:
MethodCost per part
Manufacture internallyS 11,000
Purchase from outside manufacturer$ 10,000
Acquire resale parts and repair internally$ 9,000
Purchase refurbished parts from non-certified repair shop with its extended warranty$ 8,000
The firm's CEO directs supply management to provide wing flap inventory at the lowest cost to the company, while still meeting the goal of multinational market expansion. Which of the following courses of action BEST meets the CEO's directive?