Question 16

The chief procurement officer (CPO) for a large hospital system is planning to implement a new e-sourcing system. Satellite clinics and specialty centers will be authorized to process small orders through this system, rather than sending requests to the central supply management department, as has been done in the past. Which of the following actions by the CPO will MOST likely support a successful implementation of this system?

Options:

A.

Providing regular progress reports to top management

B.

Visiting similar organizations to see how their systems operate

C.

Building a team of potential users to help define needs

D.

Scheduling on-site demonstrations of leading software systems

Discussion
Question 17

Items of low value and complexity are typically categorized as which of the following

Options:

A.

Tactical

B.

Leverage

C.

Strategic

D.

Critical

Discussion
Question 18

Which of the following is the FIRST step in developing a negotiation plan?

Options:

A.

Engage with the internal customer and other internal stakeholders to identify their needs and wants, as well as educate them as to how supply management can add value in the negotiation process

B.

Engage in an analysis of the organization's risk tolerance, and review the key suppliers' capabilities, financials and legal and regulatory compliance, as well as the risks of supply chain disruption

C.

Review the organization's logistics category strategy by analyzing anticipated spend, how the renewal will affect purchasing leverage with other suppliers, and the current characteristics of the supply market

D.

Identify the most advantageous payment terms for the renewal through an analysis of buyer and seller cash flow considerations, early payment discount opportunities and potential third-party financing options

Discussion
Question 19

A director of supply management is tasked with determining where savings can be found in indirect cost categories. If needed, the company will consider hiring additional staff to negotiate and administer contracts. Which of the following is the FIRST step the supply manager should take?

Options:

A.

Assess skills already available in supply management

B.

Identify a cross-functional team to brainstorm solutions

C.

Develop a new supplier relationship model

D.

Establish a baseline using current spend data

Discussion
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Jan 15, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Jan 11, 2026
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Jan 4, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Jan 7, 2026
They give you a competitive edge and help you prepare better.
Page: 4 / 23
Title
Questions
Posted

CORE
PDF

$36.75  $104.99

CORE Testing Engine

$43.75  $124.99

CORE PDF + Testing Engine

$57.75  $164.99