Question 108

Which of the following are input of close project process?

Options:

A.

Project management plan

B.

Contract documentation

C.

Deliverables

D.

Al1 of the above

Discussion
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 16, 2024
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Aug 30, 2024
That’s great!!! I’ll definitely give it a try. Thanks!!!
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 109

When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?

Options:

A.

Parametric estimating

B.

Bottom-up estimating

C.

Top-down estimating

D.

Analogous estimating

Discussion
Question 110

You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

Options:

A.

$-00,000

B.

$200,00

C.

$50,000

D.

None of the above

Discussion
Question 111

Which document is best suited for tracking the assignment of all resources to specific tasks in a project?

Options:

A.

RACI mAl,x

B.

sow

C.

Staffing management plan D)0 CPI

Discussion
Page: 27 / 27