Question 76

Which of the following is not a process of project human resource management?

Options:

A.

Organizational Planning

B.

staff Acquisition

C.

Distribute Information

D.

Team Development

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Nell
Are these dumps reliable?
Ernie Oct 10, 2024
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Question 77

Completion of a product scope is measured against which of the following:

Options:

A.

WBS and WBS Dictionary

B.

Product Requirements

C.

Project Management Plan

D.

Product Management Plan

Discussion
Question 78

Which of the following relationships is rarely used in PDM (Precedence Diagramming Method)?

Options:

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Discussion
Question 79

You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which one of the following is the most important factor?

Options:

A.

Business needs

B.

Type of constraints

C.

Budget

D.

Schedule

Discussion