Question 60

What impact does a matrix organization have on project team development?

Options:

A.

No impact at all

B.

It complicates team development

C.

It simplifies team development

D.

It hinders team development completely

Discussion
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 18, 2024
That sounds really useful. I'll definitely check it out.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Question 61

The communications management plan is primarily dependent on the ____________.

Options:

A.

Length of the project

B.

Physical location of team members

C.

Specific needs of the project

D.

Project deliverables

Discussion
Question 62

A scope management plan describes __________.

Options:

A.

An assessment of the stability of the stakeholder environment

B.

A highly detailed approach to managing the work breakdown structure scope

C.

How the project scope will be managed and how scope changes will be integrated into the project

D.

The stakeholder's expectation on how changes will be identified and by what priority they will be addressed

Discussion
Question 63

Project initiation is all of the following except:

Options:

A.

A process of formally recognizing that a new project exists

B.

A process of formally recognizing that an existing project should continue into its next phase

C.

It links the project to the ongoing work of the performing organization

D.

Its inputs are product description, strategic plan, constraints, and assumptions

Discussion