PMI Updated PMI-002 Exam Questions and Answers by umaiza

Page: 5 / 27

PMI PMI-002 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: PMI-002 Dumps
Vendor: PMI Certification: CAPM
Questions: 748 Q&A's Shared By: umaiza
Question 20

Contract close out contains:

Options:

A.

Contract documentation

B.

Procurement audits

C.

Formal acceptance and closure

D.

All of the above

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 21

Which of the following is a common characteristic of most project life cycle descriptions?

Options:

A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B.

The probability of successfully completing the project is highest at the start of the project.

C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D.

a and b

Discussion
Question 22

Which of the following tools and techniques are commonly used in a Define Scope Process?

Options:

A.

Product analysis

B.

Expert Judgment

C.

Alternative Identification

D.

All of the above

Discussion
Question 23

Which of the following must be measured regularly to identify variances from the plan.

Options:

A.

Stakeholder requirements

B.

Project performance

C.

Control Schedule

D.

Project controls

Discussion