Question 40

Which of the following statements are FALSE about cost reimbursable contracts?

Options:

A.

cost-reimbursable contracts generally carry the highest risks to the buyer, as the total costs are uncertain

B.

cost-reimbursable contracts often includes incentives for meeting or exceeding project objectives

C.

cost-reimbursable contracts resemble fix unit agreements when the unit rates are preset by the buyer and seller

D.

cost-reimbursable contracts are contracts that involves payments to the seller for actual costs, plus a fee representing the sellers profit

Discussion
Question 41

You are the project manager for Tech Days Seminar Homes. Your new project assignment is to head the Days Seminar Home opening in Mountainview, CA. You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in?

Options:

A.

Project Scope Management

B.

Project Quality Management

C.

Project Integration Management

D.

Project Time Management

Discussion
Question 42

You are the project manager of a large construction project. The project objective is to construct a set of buildings in the city within 18 months from the project start date. Resources are not readily available because they are currently assigned to other projects. Nick, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Nick assigned to your project?

Options:

A.

Negotiation and influencing skills

B.

Communication and organizational skills

C.

Problem solving skills

D.

Communication skills

Discussion
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 24, 2024
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 43

A project's scope statements are developed during scope:

Options:

A.

Initiation.

B.

Verification.

C.

Planning.

D.

Definition.

Discussion
Page: 10 / 27
Title
Questions
Posted

PMI-002
PDF

$36.75  $104.99

PMI-002 Testing Engine

$43.75  $124.99

PMI-002 PDF + Testing Engine

$57.75  $164.99