PMI Updated PMI-002 Exam Questions and Answers by casey

Page: 9 / 27

PMI PMI-002 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: PMI-002 Dumps
Vendor: PMI Certification: CAPM
Questions: 748 Q&A's Shared By: casey
Question 36

Which of the following are inputs of the Develop Project Charter process?

Options:

A.

Project statement of work, Contract, Business case and organizational process assets

B.

Project SOW, project selection methods, and enterprise environmental factors

C.

Contract, project selection methods, enterprise environmental factors, and organizational process assets

D.

Contract, project SOW, enterprise environmental factors, and organizational process assets

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 26, 2024
That's great to know. So, you think new students should buy these dumps?
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 16, 2024
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Question 37

You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?

Options:

A.

Planning

B.

Monitoring and Controlling

C.

Executing

D.

Initiating

Discussion
Question 38

You are the project manager and are considering recommending a project that costs $280,000; expected inflows are $10,000 per quarter for the first two years and then $25,000 per quarter thereafter. What is the payback period?

Options:

A.

48 months

B.

40 months

C.

36 months

D.

50 months

Discussion
Question 39

If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?

Options:

A.

0-413

B.

0-82

C.

1-06

D.

1-142

Discussion