Question 68

Which of the following statements concerning compromise as a conflict resolution is false?

Options:

A.

Neither party wins but both parties get some degree of satisfaction

B.

Important aspects of the project may be hindered in order to achieve personal objectives

C.

Compromise is generally considered a lose-lose situation

D.

A Definitive resolution is seldom achieved

Discussion
Question 69

Risks are accepted when __________.

Options:

A.

You develop a contingency plan to execute in case the risk event occurs.

B.

To eliminate the threat entirely.

C.

You transfer the risk to another party.

D.

Taking early action to reduce probably of risk rather repair the damage after risk has occurred.

Discussion
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Aug 30, 2024
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Question 70

A schedule activity may start 5 days before the predecessor activity finishes. This is an example of ______________.

Options:

A.

Finish-to-Start

B.

Finish-to-Finish

C.

Start-to-Start

D.

Start-to-Finish

Discussion
Question 71

A technique for resolving conflict in which the parties agree to have a neutral third party hear the dispute and make a decision is called ____________.

Options:

A.

Negotiation

B.

Arbitration

C.

Smoothing

D.

Forcing

Discussion
Page: 17 / 27
Title
Questions
Posted

PMI-002
PDF

$36.75  $104.99

PMI-002 Testing Engine

$43.75  $124.99

PMI-002 PDF + Testing Engine

$57.75  $164.99