Question 84

A contingency plan is executed when _____________.

Options:

A.

A risks is identified

B.

An identified risk occurs

C.

When a workaround is needed

D.

Al1 of the above

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 3, 2024
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 85

Mathematical models using linear, dynamic, integer, or algorithm models are considered _____________.

Options:

A.

Project selection methods

B.

Project selection criteria

C.

A form of expert judgment

D.

A form of historical information

Discussion
Question 86

A risk response which involves eliminating a threat is called ________.

Options:

A.

Mitigation

B.

Deflection

C.

Avoidance

D.

Transfer

Discussion
Question 87

Which of the following is not considered a cost of non-conformance to quality?

Options:

A.

Scrap

B.

Rework

C.

Expediting

D.

Process control

Discussion