Question 48

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.

What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?

Options:

A.

Note stakeholder communication needs in the program charter and document their expectations in the benefits sustainment plan.

B.

Note stakeholder communication needs in the communications management plan and document their expectations in the benefits management plan.

C.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits management plan.

D.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits sustainment plan.

Discussion
Question 49

The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system’s cost. The program manager has provided monthly performance reports throughout the program’s life cycle.

Which of the following would the customer be interested in reviewing?

Options:

A.

Estimate to complete

B.

Estimate at completion

C.

Original cost baseline

D.

Cost performance index

Discussion
Question 50

The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.

Where is this expectation documented?

Options:

A.

Program quality standards

B.

Customer management plan

C.

Benefits management plan

D.

Benefits sustainment plan

Discussion
Question 51

Which of the following increases when one fast tracks the project?

Options:

A.

Resource

B.

Risk

C.

Cost

D.

Communication

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 2, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Sep 10, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 1, 2026
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Sep 11, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Nell
Are these dumps reliable?
Ernie Sep 23, 2026
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Page: 12 / 16

PgMP
PDF

$31.5  $104.99

PgMP Testing Engine

$37.5  $124.99

PgMP PDF + Testing Engine

$49.5  $164.99