Question 48

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.

What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?

Options:

A.

Note stakeholder communication needs in the program charter and document their expectations in the benefits sustainment plan.

B.

Note stakeholder communication needs in the communications management plan and document their expectations in the benefits management plan.

C.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits management plan.

D.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits sustainment plan.

Discussion
Question 49

The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system’s cost. The program manager has provided monthly performance reports throughout the program’s life cycle.

Which of the following would the customer be interested in reviewing?

Options:

A.

Estimate to complete

B.

Estimate at completion

C.

Original cost baseline

D.

Cost performance index

Discussion
Question 50

The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.

Where is this expectation documented?

Options:

A.

Program quality standards

B.

Customer management plan

C.

Benefits management plan

D.

Benefits sustainment plan

Discussion
Question 51

Which of the following increases when one fast tracks the project?

Options:

A.

Resource

B.

Risk

C.

Cost

D.

Communication

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Sep 4, 2026
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Sep 16, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Sep 12, 2026
Good point. Thanks for the advice. I'll definitely keep that in mind.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Sep 6, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Page: 12 / 16

PgMP
PDF

$31.5  $104.99

PgMP Testing Engine

$37.5  $124.99

PgMP PDF + Testing Engine

$49.5  $164.99