Question 60

You are the program manager for the NHQ Program. Your program has a budget of

$4,500,000 and has lasted for two years. Your program has just completed its final

deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?

Options:

A.

The customer must now sign the program scope.

B.

The customer must now sign the payment for the program work.

C.

The customer must now sign the certificate of program closure.

D.

The customer must now sign the operational transfer agreement.

Discussion
Question 61

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Options:

A.

Change requests

B.

Performance reports

C.

Forecasts

D.

Earned value management

Discussion
Question 62

A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program.

What should the program manager do first?

Options:

A.

Update the benefits management plan, and send it to stakeholders for review.

B.

Document the impact on the program, then present the findings to the steering committee to determine next steps.

C.

Conduct a risk assessment associated with an accelerated schedule, update the risk register, and request steering committee approval.

D.

Revise the program schedule to adapt to an accelerated delivery of benefits, and present it to the steering committee for approval.

Discussion
Nia
Why are these Dumps so important for students these days?
Mary Mar 23, 2026
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Mar 17, 2026
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Mar 14, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Mar 24, 2026
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Question 63

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program.

The benefits register should include which of the following?

Options:

A.

List of planned benefits, earned value (EV), and responsible person

B.

List of planned benefits, measurement method, and component mapping

C.

List of planned benefits, benefit creator, and realization date

D.

List of planned benefits, stakeholders, and risk level