New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PgMP Exam Questions and Answers by rylee

Page: 16 / 16

PMI PgMP Exam Overview :

Exam Name: Program Management Professional (PgMP)
Exam Code: PgMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 452 Q&A's Shared By: rylee
Question 64

The program manager completed the program's benefits analysis and planning activities.

What will this ensure for the program?

Options:

A.

Information necessary to establish key benefit performance indicators

B.

A transition plan to facilitate the ongoing realization of benefits

C.

A plan to monitor performance due to operational, financial, and benefits changes

D.

A benefits management plan to guide the work through the remainder of the program

Discussion
Question 65

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options:

A.

Resource breakdown structure

B.

Resource management chart

C.

Stakeholder analysis chart

D.

RACI chart

Discussion
Andrew
Are these dumps helpful?
Jeremiah Dec 22, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Dec 11, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Dec 22, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Dec 17, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 66

Wan is the program manager for his organization. He has been hearing reports that some

project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Options:

A.

The schedule to complete the work will take longer.

B.

The cost of the program and project will increase.

C.

The risks of failure will increase.

D.

The morale of the project managers will decline.

Discussion
Question 67

Which one of the following is not considered one of the three components of the Iron Triangle?

Options:

A.

Time

B.

Cost

C.

Scope

D.

Quality

Discussion
Page: 16 / 16

PgMP
PDF

$36.75  $104.99

PgMP Testing Engine

$43.75  $124.99

PgMP PDF + Testing Engine

$57.75  $164.99