Question 64

The program manager completed the program's benefits analysis and planning activities.

What will this ensure for the program?

Options:

A.

Information necessary to establish key benefit performance indicators

B.

A transition plan to facilitate the ongoing realization of benefits

C.

A plan to monitor performance due to operational, financial, and benefits changes

D.

A benefits management plan to guide the work through the remainder of the program

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jan 12, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Jan 23, 2026
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Neve
Will I be able to achieve success after using these dumps?
Rohan Jan 27, 2026
Absolutely. It's a great way to increase your chances of success.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Jan 3, 2026
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Question 65

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options:

A.

Resource breakdown structure

B.

Resource management chart

C.

Stakeholder analysis chart

D.

RACI chart

Discussion
Question 66

Wan is the program manager for his organization. He has been hearing reports that some

project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Options:

A.

The schedule to complete the work will take longer.

B.

The cost of the program and project will increase.

C.

The risks of failure will increase.

D.

The morale of the project managers will decline.

Discussion
Question 67

Which one of the following is not considered one of the three components of the Iron Triangle?

Options:

A.

Time

B.

Cost

C.

Scope

D.

Quality

Discussion