PMI Updated PgMP Exam Questions and Answers by rylee

Page: 16 / 16

PMI PgMP Exam Overview :

Exam Name: Program Management Professional (PgMP)
Exam Code: PgMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 452 Q&A's Shared By: rylee
Question 64

The program manager completed the program's benefits analysis and planning activities.

What will this ensure for the program?

Options:

A.

Information necessary to establish key benefit performance indicators

B.

A transition plan to facilitate the ongoing realization of benefits

C.

A plan to monitor performance due to operational, financial, and benefits changes

D.

A benefits management plan to guide the work through the remainder of the program

Discussion
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Oct 14, 2025
YES….. I saw the same questions in the exam.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Oct 3, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Oct 2, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 27, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Question 65

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options:

A.

Resource breakdown structure

B.

Resource management chart

C.

Stakeholder analysis chart

D.

RACI chart

Discussion
Question 66

Wan is the program manager for his organization. He has been hearing reports that some

project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Options:

A.

The schedule to complete the work will take longer.

B.

The cost of the program and project will increase.

C.

The risks of failure will increase.

D.

The morale of the project managers will decline.

Discussion
Question 67

Which one of the following is not considered one of the three components of the Iron Triangle?

Options:

A.

Time

B.

Cost

C.

Scope

D.

Quality

Discussion