Question 56

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?

Options:

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member.

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.

D.

Create an online message board so team members can see and respond to everyone’s ideas.

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Nov 7, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Nov 2, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Nov 7, 2025
Me too. They're a lifesaver!
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Nov 19, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Question 57

On which of the following documents you work throughout the risk management processes?

Options:

A.

Risk management plan

B.

Project management plan

C.

Risk register

D.

Project charter

Discussion
Question 58

You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

Options:

A.

Indirect costs

B.

Cost of doing business

C.

Direct costs

D.

Cost of conformance quality

Discussion
Question 59

Who makes Go/No-Go decisions during phase gate reviews?

Options:

A.

Program Governance board

B.

Program Manager

C.

Board of Project Managers

D.

Stakeholders

Discussion