Question 56

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?

Options:

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member.

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.

D.

Create an online message board so team members can see and respond to everyone’s ideas.

Discussion
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Dec 5, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Dec 17, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Dec 20, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Dec 16, 2025
Me too. They're a lifesaver!
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Dec 20, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Question 57

On which of the following documents you work throughout the risk management processes?

Options:

A.

Risk management plan

B.

Project management plan

C.

Risk register

D.

Project charter

Discussion
Question 58

You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

Options:

A.

Indirect costs

B.

Cost of doing business

C.

Direct costs

D.

Cost of conformance quality

Discussion
Question 59

Who makes Go/No-Go decisions during phase gate reviews?

Options:

A.

Program Governance board

B.

Program Manager

C.

Board of Project Managers

D.

Stakeholders

Discussion