Question 56

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?

Options:

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member.

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.

D.

Create an online message board so team members can see and respond to everyone’s ideas.

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Dec 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Dec 16, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Dec 15, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Dec 22, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 57

On which of the following documents you work throughout the risk management processes?

Options:

A.

Risk management plan

B.

Project management plan

C.

Risk register

D.

Project charter

Discussion
Question 58

You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

Options:

A.

Indirect costs

B.

Cost of doing business

C.

Direct costs

D.

Cost of conformance quality

Discussion
Question 59

Who makes Go/No-Go decisions during phase gate reviews?

Options:

A.

Program Governance board

B.

Program Manager

C.

Board of Project Managers

D.

Stakeholders

Discussion