Month End Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PgMP Exam Questions and Answers by essa

Page: 2 / 16

PMI PgMP Exam Overview :

Exam Name: Program Management Professional (PgMP)
Exam Code: PgMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 452 Q&A's Shared By: essa
Question 8

A component project of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations.

What should the program manager do next?

Options:

A.

Reassign the component project manager to another component project or activity

B.

Verify that the benefits were delivered and authorize component project closure

C.

Conduct a program audit to confirm that the component project is complete

D.

Keep the component project open until the program benefits are realized

Discussion
Question 9

A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program’s benefits sustainment and transition plan. What should the program manager do to create this plan?

Options:

A.

Identify key measures to compare expected benefits in the benefits management plan with actual performance once benefits sustainment and program transition starts.

B.

Assign creation of the benefits sustainment plan to the organization responsible for monitoring and controlling the sustainment period.

C.

Interview stakeholders, and revise the benefits management plan to provide new insight into the program’s execution and benefits sustainment period.

D.

Update the benefits management plan, and provide a copy to the organization responsible for measuring the sustainment period.

Discussion
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Question 10

You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete. What should you do next in regard to the vendor's invoice?

Options:

A.

Approve the payment request

B.

Finalize the performance report

C.

Examine the contract

D.

Complete a financial audit of the work

Discussion
Question 11

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

Options:

A.

Select the best bid from the prequalified vendor list.

B.

Accept the bid from the new vendor and document the decision.

C.

Advise the sponsor of a possible conflict of interest prior to awarding the bid.

D.

Add the new vendor to the prequalified list and replace the project manager.

Discussion
Page: 2 / 16

PgMP
PDF

$36.75  $104.99

PgMP Testing Engine

$43.75  $124.99

PgMP PDF + Testing Engine

$57.75  $164.99