Question 28

Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?

Options:

A.

Risk avoidance

B.

Risk transference

C.

Risk mitigation

D.

Risk acceptance

Discussion
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Sep 28, 2024
did you use PDF or Engine? Which one is most useful?
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Sep 25, 2024
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Question 29

Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

Options:

A.

Operational transfer alliance plan

B.

Program milestone list

C.

Program transition agreement

D.

Program scope statement

Discussion
Question 30

An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks.

To address this issue, what should the IT program manager do next?

Options:

A.

Schedule a meeting with the business team to discuss transferring the two business team resources to the IT team; update the program risk register to include risk mitigation steps.

B.

Escalate the lack of commitment by the business team to the program steering committee; hire a new project resource to complete the required tasks; update the program risk register to include risk mitigation steps.

C.

Review and clarify the business team’s program roles and responsibilities; determine the schedule impact on benefits delivery; direct the IT project manager to meet with the business team to ensure dependencies are understood and that the appropriate resources can be made available.

D.

Modify the program milestone dates to include a larger contingency; determine the impact on the project implementation date; update the benefits management plan.

Discussion
Question 31

A program to implement a company's new system is nearing completion and the program manager attempts to close the program. However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.

To prevent this concern in the future, which of the following should occur?

Options:

A.

Collaboration with the operational staff to develop the benefits sustainment plan

B.

Communication of the new capabilities' benefits to the operational staff

C.

Development and execution of a benefits transition plan to prepare the operational areas

D.

Identification of the risk in the program risk register and development of a plan to address the risk

Discussion