Question 44

You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were QUESTION NO:s about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Options:

A.

Request for bid documents

B.

Proposals

C.

Statement of work

D.

Program management plan

Discussion
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 45

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.

What should the program manager do next?

Options:

A.

Escalate the issue to the stakeholder’s supervisor

B.

Escalate the issue to the program governance board, as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Discussion
Question 46

What project management term would you associated with a predetermined budget you’re your program?

Options:

A.

Program governance

B.

Constraint

C.

Cost baseline

D.

Assumption

Discussion
Question 47

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Options:

A.

Negative ten percent B. .75

B.

$300,000 D. $225,000

Discussion