Question 44

You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were QUESTION NO:s about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Options:

A.

Request for bid documents

B.

Proposals

C.

Statement of work

D.

Program management plan

Discussion
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Aug 25, 2026
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Aug 11, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Aug 3, 2026
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Aug 13, 2026
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Question 45

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.

What should the program manager do next?

Options:

A.

Escalate the issue to the stakeholder’s supervisor

B.

Escalate the issue to the program governance board, as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Discussion
Question 46

What project management term would you associated with a predetermined budget you’re your program?

Options:

A.

Program governance

B.

Constraint

C.

Cost baseline

D.

Assumption

Discussion
Question 47

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Options:

A.

Negative ten percent B. .75

B.

$300,000 D. $225,000

Discussion