Question 44

You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were QUESTION NO:s about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Options:

A.

Request for bid documents

B.

Proposals

C.

Statement of work

D.

Program management plan

Discussion
Robin
Cramkey is highly recommended.
Jonah Oct 26, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Oct 19, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Oct 25, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 45

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.

What should the program manager do next?

Options:

A.

Escalate the issue to the stakeholder’s supervisor

B.

Escalate the issue to the program governance board, as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Discussion
Question 46

What project management term would you associated with a predetermined budget you’re your program?

Options:

A.

Program governance

B.

Constraint

C.

Cost baseline

D.

Assumption

Discussion
Question 47

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Options:

A.

Negative ten percent B. .75

B.

$300,000 D. $225,000

Discussion