Question 16

You are the program manager for your organization. Your current program has a budget at completion of

$3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

Options:

A.

$2,656,500

B.

There is not enough information to know. C. $3,795,000

C.

$1,035,000

Discussion
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Nov 10, 2025
Great. Yes they are really effective
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Nov 7, 2025
That's great. I think I'll give Cramkey Dumps a try.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Nov 11, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Nov 3, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Nov 19, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Question 17

Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

Options:

A.

Deadlines for project milestones

B.

Building codes

C.

A predetermined program budget

D.

Weather

Discussion
Question 18

You are the program manager for the BHN Program. Your program has 122 stakeholders that you'll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?

Options:

A.

244

B.

122

C.

14,884

D.

7,381

Discussion
Question 19

There are 1,500 doors to be installed in Tom's program. Each of the 1,500 doors is required by the building code to swing into the room rather than swing out into the hallways. It has come to Tom's attention that part of the team installing the doors has installed nearly 200 doors to swing into the hallway rather than into the rooms. Tom instructs the team to fix the problem. What type of action has Tom taken in this instance?

Options:

A.

Scope control

B.

Defect repair validation

C.

Team development

D.

Defect repair