Question 76

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

Options:

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Discussion
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Aug 18, 2024
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Andrew
Are these dumps helpful?
Jeremiah Oct 27, 2024
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Question 77

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the scrum master do?

Options:

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Discussion
Question 78

During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.

What should the agile practitioner do?

Options:

A.

Tell the team that this is unacceptable for the upcoming project.

B.

Implement the workaround since performance issues can be addressed in the next iteration.

C.

Calculate the cost of redoing the architecture and seek management approval.

D.

Brainstorm with the team to identify a solution.

Discussion
Question 79

During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.

How should the scrum master respond?

Options:

A.

Project velocity should be stable overtime.

B.

Moving velocity from 27 to 35 is a decrease in productivity.

C.

A burndown chart compares planned versus actual, not velocity.

D.

Velocity is iterative and will only be used for sprint numbers.

Discussion