Question 16

An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:

Options:

A.

procurement processes by requiring vendors to ship materials as needed.

B.

project cost management by making incremental payments on contracts.

C.

customer satisfaction by specifying project shipping dates in the contract.

D.

project Return on Investment (ROI) by releasing individual features to market.

Discussion
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Question 17

Which of the following best describes a core belief of Agile?

Options:

A.

The best customer feedback comes near the end of the project when there is working software to review.

B.

Project status can be gauged by frequently reviewing completed milestones as reflected in the plan.

C.

Working solutions are the most accurate way of seeing the progress of the effort.

D.

Unique skill sets are harnessed when team members play different roles on a project.

Discussion
Question 18

In the Lean process, the focus is on:

Options:

A.

Managing team efficiency.

B.

Optimizing completed work across the process stream.

C.

Using the optimal resources.

D.

Cross training the team to eliminate bottlenecks.

Discussion
Question 19

Who is responsible for determining the business value of each feature?

Options:

A.

Product Owner

B.

Steering committee

C.

ScrumMaster

D.

Team

Discussion