Exam Name: | PMI Agile Certified Practitioner (PMI-ACP) | ||
Exam Code: | PMI-200 Dumps | ||
Vendor: | PMI | Certification: | PMI ACP |
Questions: | 482 Q&A's | Shared By: | oliwier |
An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.
What is the sponsor looking at?
The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?
A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remainingstories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).
What should the team tell the sponsor at this point in the planning process?
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?