Pre-Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

PMI Updated PMI-200 Exam Questions and Answers by oliwier

Page: 9 / 35

PMI PMI-200 Exam Overview :

Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-200 Dumps
Vendor: PMI Certification: PMI ACP
Questions: 482 Q&A's Shared By: oliwier
Question 36

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

Options:

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

Discussion
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Aug 30, 2024
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Question 37

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Discussion
Question 38

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remainingstories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

Options:

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.

B.

They can provide an anticipated date with the assumption that conditions will be ideal.

C.

They can provide a broad range but cannot realistically set a target release date until the team's velocity stabilizes.

D.

They will send an update when all of the stories are estimated and prioritized in the backlog.

Discussion
Question 39

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.

What can an agile practitioner conclude about team A and team B's estimates?

Options:

A.

Team B has underestimated scope compared to team A.

B.

Team A is more confident in delivering velocity than team B.

C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.

Both teams have estimated the project to be of same size.

Discussion
Page: 9 / 35
Title
Questions
Posted

PMI-200
PDF

$42  $104.99

PMI-200 Testing Engine

$50  $124.99

PMI-200 PDF + Testing Engine

$66  $164.99