Question 8

Estimating costs for an Agile project starts with which of the following types of meetings?

Options:

A.

Project Retrospective

B.

Steering Committee

C.

Release Planning

D.

Sprint Planning

Discussion
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 9

On a project using eXtreme Programming (XP), a customer test is a:

Options:

A.

Technique to determine if the software is easy for customer use.

B.

Tool for a customer to verify the business requirements.

C.

Technique to determine if a customer will use a software feature.

D.

Test for determining if a customer will purchase the product.

Discussion
Question 10

A ScrumMaster:

Options:

A.

prioritizes the work for each iteration.

B.

directs the activities of the team.

C.

provides leadership, guidance, and coaching.

D.

manages the project scope and budget.

Discussion
Question 11

On what should Agile estimates be based?

Options:

A.

A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan

B.

A disciplined iteration schedule, which improves predictability, combined with reaction to changes

C.

Ball park figures collected from past Agile projects with scopes similar to the current project

D.

Initial resource breakdown based on the available person days in the full project duration

Discussion