Question 124

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

Options:

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Discussion
Question 125

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

Options:

A.

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.

B.

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.

C.

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.

D.

Implement a spike lo enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working

Discussion
Question 126

A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?

Options:

A.

Engage the team to determine the sprint velocity based on previous agile projects.

B.

Average the sprint velocity based on input from team members

C.

Share the sprint velocity obtained from the sponsor with the team

D.

Run multiple sprints before determining the sprint velocity with the team.

Discussion
Question 127

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

Options:

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Page: 31 / 35
Title
Questions
Posted

PMI-ACP
PDF

$36.75  $104.99

PMI-ACP Testing Engine

$43.75  $124.99

PMI-ACP PDF + Testing Engine

$57.75  $164.99